Warehouse

DC3 distribution warehouse at ProLogis Park, Stoke

DC3 distribution warehouse at ProLogis Park, Stoke

Guidance report: industrial warehouses

The second in the series of five guidance reports, modelled on the DC3 distribution warehouse at Prologis Park, Stoke has been published.

The key findings include:

  • A package of compatible, cost-effective energy efficiency measures are possible that would yield a 54% reduction in regulated emissions relative to the Part L 2006 compliant base case warehouse and yield a 25-year net present value saving of -£2,470,354.
  • The estimated capital cost uplift of the steel portal frame base case distribution warehouse for achieving the following three BREEAM assessments is:
    • 0.04% to achieve BREEAM ‘Very Good’
    • 0.4% to achieve BREEAM ‘Excellent’
    • 4.8% to achieve BREEAM ‘Outstanding’
  • Relative to the base case steel frame warehouse, a pre-cast concrete and glulam framed building was found to have a 14% higher carbon footprint (embodied carbon impact). A steel frame structure with northlights had a 7% higher impact than the base case warehouse.

Available in PDF now.

Download report (PDF)

REGISTER HERE for notification when future publications become available

More…

Call or email us for further details or advice on the Target Zero project

Target Zero Information Line
+44 (0)1709 82 55 44 Email
.(JavaScript must be enabled to view this email address) or complete an enquiry form